Kirby’s council voted 6-0 in September 2024 to pay $31,800, half the cost of additional off-duty officers for Ackerman Road, under change order 12. The council’s $31,800 share made additional officer coverage a city cost on the Ackerman Road project.
The engineer’s March 2024 summary put the original Ackerman Road contract at $10,066,581.70 and said it carried no contingency. It recorded an earlier $36,154.98 change order for off-duty police officers, before the council’s later agreement to share another officer cost.
Together, the first four changes listed in that summary lowered the contract amount by $144,290.46. The reduction in order 1 was larger than the three additions that followed it.
Where and when
The places and times below come from the official pages linked with each one.
- Site
Ackerman Road
Ackerman Road, Kirby
Road project discussed in the cited contract summary and council minutes.
How the early changes added up
| Change order | Amount |
|---|---|
| 1 | −$204,277.85 |
| 2 | $902.49 |
| 3: off-duty officers | $36,154.98 |
| 4 | $22,929.92 |
The four listed amounts sum to a $144,290.46 decrease.
The same summary described a $32,025 request under change order 5 for 61 additional mailboxes at the original $525 unit price. The engineer agreed that work was necessary. That assessment described the request; it was not a council vote on order 5.