Vantage TX 11’s draft federal operating permit would govern listed equipment at its data center on Omicron Drive in San Antonio. The proposed permit concerns how the facility operates under applicable air rules; it is not a new construction approval.
At full build-out, Vantage TX 11’s plan describes 86 diesel emergency generators at 14720 Omicron Dr in San Antonio. The Statement of Basis says they are intended for power outages and routine maintenance and readiness tests. That full-build-out figure describes the plan, not a verified count of generators already installed or running.
From the source record
The draft permit would govern operation of listed units under existing applicable conditions.Texas Commission on Environmental Quality ↗
Where and when
Each number on the map matches the list below. Tap a number for its times and source.
Loading map…
Map data © OpenStreetMap contributors. Use two fingers to move the map on a phone.
- Site
14720 Omicron Dr, San Antonio
Facility named in TCEQ’s Statement of Basis
What this permit would do
The permit is marked Initial Issuance-Draft. Its operating conditions would apply to the units listed in the permit if TCEQ issues it. The Statement of Basis identifies nitrogen oxides as the facility’s major-source pollutant.
The Statement of Basis says this federal operating permit does not authorize new emissions or construction. Those activities require separate New Source Review authorization. For neighbors weighing what the filing means, the distinction matters: the draft collects operating requirements for the facility; it does not by itself approve a new generator or an increase in emissions.
What to watch next
Residents can inspect the draft permit’s listed units and conditions alongside TCEQ’s explanation of the facility in the Statement of Basis. The next useful records are the applicable New Source Review authorizations, any public notice setting a comment deadline, and TCEQ’s final decision on this draft.